5.2 Contractor may make Application for Payment for Work completed during the Project <br />at intervals of not more than once a month. Contractor's Application for Payment shall include <br />partial release(s) of liens or consent of Surety relative to the portion of the Work, which is the <br />subject of the Application for Payment and any other information required by the City. Each <br />Application for Payment shall be submitted in triplicate to the City for approval. <br />5.3 The City may withhold, in whole or in part, payment to such extent as may be necessary to <br />protect itself from loss on account of: <br />5.3.1 Defective Work not remedied by Contractor. <br />5.3.2 Claims filed or reasonable evidence indicating probable filing of <br />claims by other parties against Contractor or the City because of <br />Contractor's performance. <br />5.3.3 Failure of Contractor to make payments properly to Sub - Contractors or for <br />material or labor. <br />5.3.4 Liquidated damages. <br />5.3.5 Failure of Contractor to comply with other provisions of this Agreement. <br />5.4 Upon receipt of written notice from Contractor that the Work is ready for final <br />inspection and acceptance, the City will make an inspection thereof. If the City finds the Work <br />acceptable, the requisite documents have been submitted and the requirements of the Contract <br />Documents fully satisfied, and all conditions of the permits and regulatory agencies have been <br />met, a Final Certificate for Payment will be issued by the City, stating that the requirements of <br />the Contract Documents have been performed and the Work is ready for acceptance under the <br />terms and conditions thereof. <br />5.5 Before issuance of the Final Certificate for Payment, Contractor shall deliver to the <br />City a complete release of all liens arising out of this Agreement, or receipts in full in lieu thereof, <br />an affidavit certifying that all suppliers and Sub - Contractors have been paid in full and that all <br />other indebtedness connected with the Work has been paid, and a consent of the surety to final <br />payment; and the final bill of materials, if required, and Application for Payment. <br />Contractor shall deliver the written Contractor's and all Manufacturers warranties prior to <br />issuance of the Final Certificate for Payment. <br />5.6 Final payment shall be made only after the City has reviewed and approved the final <br />application for payment. The acceptance of final payment shall constitute a waiver of all <br />claims by Contractor, except those previously made in strict accordance with the provisions of <br />the Agreement and identified by Contractor as unsettled at the time of the application for final <br />payment. <br />ARTICLE 6. REQUESTS FOR INFORMATION (RFI) <br />The Contractor shall submit in writing a Request for Information (RFI) to the City where the <br />Contractor believes that the specifications or drawings are unclear or conflict. All requests <br />must be submitted in a manner that clearly identifies the drawing and /or specification section <br />where clarification or interpretation is being requested. <br />6 <br />