Laserfiche WebLink
MORIARTY <br />Miami Beach Club <br />4/22/25 <br />CONSTRUCTION SCHEDULE <br />DESCRIPTION TIME AT END OF <br />Early Works <br />DSM / TSM / Piles / Excavation / Rock 26 wks 26 wks <br />Waterproofing 4 wks 31 wks <br />Building -Start of Construction ** <br />Mat -Hydro -static slab (P-0) <br />8 wks <br />8 wks <br />First Lift-Ext-walls <br />4 wks <br />12 wks <br />Perm Walls and (P-1) deck <br />8 wks <br />25 wks <br />P-2 <br />4 wks <br />29 wks <br />Lobby Level (Floor 3) <br />4 wks <br />33 wks <br />Amenity Floors 4 and 5 <br />6 wks <br />39 wks <br />Floors 6 thru 25 <br />20 wks <br />59 wks <br />Floors 26 to 27 <br />3 wks <br />62 wks <br />Floors 28 to 60 <br />34. wks <br />96 wks <br />Floors 61 and 62 PHS <br />3 wks <br />99 wks <br />Roof and EMR <br />4 wks <br />* 103 wks <br />Elevator — Car turnover <br />20 wks <br />123 wks <br />Units/ Exterior <br />52 wks* <br />155 wks <br />Life Safety <br />52 wks* <br />155 wks <br />TCO #1— 100% Amenities and units thru 27 <br />0 wks <br />155 wks <br />TCO #2 — Units 28 thru 60 <br />4 wks <br />159 wks <br />TCO #3 — PH's 61 and 62 <br />4 wks <br />163 wks <br />** Start of construction Rebar in the hole of the Mat Foundation <br />CITY op <br />y \SLES� <br />�� ,F <br />z_� j� <br />RECEIVED <br />PZ2025-08 <br />5/13/2025 <br />PLANNING & ZONING DEPT. <br />327 <br />