17. Need clarification on doing %2 street and then the other V2 of the street, in his opinion it <br /> doesn't work. <br /> The Contractor may provide its own MOT plans. Cite will review and approve as <br /> required, but access to all residents must be maintained at all times <br /> 18. What is the City's estimate for this project? <br /> S3.9 Million Dollars. <br /> 19. Are there any restrictions for noise or lane closures? <br /> Specific working hours are indicated in the bid documents. However the City will <br /> consider the circumstances involved. <br /> 20. Is there any incentive/disincentive for damages or liquidated damages? <br /> Incentive is limited to 51,500 per day, not to exceed 5100,000.00, if job is completed <br /> before the end date and the project is ready for final payment date. YES on liquidated <br /> damages. <br /> 21. Quality control of product by the City or contractor? <br /> QC by the contractor; the City resents the right to verify all products. <br /> 22. Does that include asphalt? <br /> YES. <br /> 23. Is there any known contamination? <br /> NO. <br /> 24. Drainage Wells: add a lump sum on each? Include structure? The well itself, longer or <br /> shorter, some are 200', 120' 150', no information included in this. <br /> Payment for drainage wells was itemized. See Summary of Quantities sheet. <br /> 25. The plan indicated a significant band of muck, it is marked as an elevation this may not be <br /> desirable where drainage is, excavation item to use for removal and disposal? <br /> See sheet 37 for pipe bedding. Also, see note #17 on sheet # 5 <br /> 26. Clarification, in the event that muck with elevation below the pipe, so don't build pipe on <br /> muck? Correct,do not build on muck. Is there going to be a requirement to over excavate <br /> and provide for a foundation? <br /> Cost of trench excavation,disposal of excess of material removal, backfill with suitable <br /> selected material,reposition of pavement,landscaped areas,"SHALL'BE INCLUDED <br /> IN THE UNIT PRICE FOR SEWER CONSTRUCTION", and comply with FDOT <br /> governing standards and specifications as stated. <br /> 27. Where is the draincrete called out to under drain details to be used, and what are the limits <br /> and dimensions for the draincrete? A draincrete is porous concrete that allows water to go <br /> through as we saw in the plans, it wasn't in the list of items, they found it somewhere else. <br /> Draincrete requirement was removed from Swale Trench Detail(Underdrain)on sheet <br /> Bid 07-10-02 Pre-Bid Conference QA Page 3 Of 6 <br />