<br />01700 - 2/5 <br />A. Preliminary Procedures: Submit certification by Contractor that Work has been <br />completed in accordance with the Contract Documents to the knowledge of the <br />Contractor. Before requesting final inspection, complete the following. <br />1. Submit the final payment request with releases and supporting documentation. <br />Include insurance certificates for products and completed operations where <br />required. <br />2. Submit a certified copy of the City's final inspection list of items to be <br />completed or corrected. The certified copy of the list shall state that each item <br />has been completed. <br />3. Submit final meter readings for utilities, a measured record of stored fuel, and <br />similar data as of the date of Substantial Completion. <br />4. Submit consent of surety to final payment. <br />5. Submit evidence of final, continuing insurance coverage complying with <br />insurance requirements. <br />6. Release of Liens (from the Prime, and all Subcontractors, Vendors and <br />Suppliers). <br />7. Submit Maintenance Bond. <br />8. Submit final Record Drawings and final closed out permits. <br />B. Re-inspection Procedure: The City will re-inspect the Work upon receipt of notice <br />that the Work, including inspection list items from earlier inspections, has been <br />completed. <br />1. Upon completion of re-inspection, the City will advise the Contractor of Work <br />that is incomplete or of obligations that have not been fulfilled but are required <br />for final acceptance. <br />2. If necessary, re-inspection will be repeated. <br />C. Return all keys and other items furnished by the City. The contractor shall forfeit his <br />deposit for keys and other items that are not returned. <br />1.04 RECORD DOCUMENT SUBMITTALS: <br />A. General: Do not use record documents for construction purposes. Protect record <br />documents from deterioration and loss in a secure, fire-resistant location. Provide <br />access to record documents for the City's reference during normal working hours. <br />B. Record Drawings: Maintain a clean, undamaged set of blue or black line white-prints <br />of Contract Drawings and Shop Drawings. Mark the set to show the actual <br />installation where the installation varies substantially from the Work as originally <br />shown. Mark which drawing is most capable of showing conditions fully and <br />accurately. Where Shop Drawings are used, record a cross-reference at the <br />corresponding location on the Contract Drawings. Give particular attention to <br />concealed elements that would be difficult to measure and record at a later date. <br />Call attention to each entry by drawing a "cloud" around the areas affected. <br />C. The CITY will make electronic copies of whatever electronic versions of the bid plans <br />exist, available to the CONTRACTOR for Record Drawing purposes. <br />CONTRACTOR must obtain the concurrence of the Resident Engineer as to form <br />and content of record information provided in electronic format prior to proceeding, <br />but in general, information similar to that shown below needs to be similarly provided. <br />1. Record information concurrently with construction progress.