<br />03300 - 11/22 <br />PART 3 - EXECUTION <br />3.01 PROPORTIONING AND MIXING: <br />A. Proportioning of the mix shall conform to the requirements of Chapter 3 <br />"Proportioning" of ACI 301. <br />B. Mixing shall conform to the requirements of Chapter 7 of ACI 301. <br />C. Slumps shall be as indicated herein. <br />D. Retempering of concrete or mortar that has partially hardened shall not be permitted. <br />3.02 PREPARATION OF SURFACES FOR CONCRETING: <br />A. General: Earth surfaces shall be thoroughly wetted by sprinkling prior to the placing <br />of any concrete, and these surfaces shall be kept moist by frequent sprinkling up to <br />the time of placing concrete thereon. The surface shall be free from standing water, <br />mud, and debris at the time of placing concrete. <br />B. Vapor Barrier <br />1. Vapor Barrier shall be installed under on-grade building floor slabs of <br />occupiable (non-hydraulic) structures and at other locations indicated. <br />2. Base shall be leveled, compacted, and tamped per SECTION 02200 <br />Earthwork. Remove sharp edges, projection materials and roughness that <br />might penetrate vapor barrier. Install barrier with width parallel with the <br />direction of the pour of the concrete. <br />3. Place, protect, and repair defects in sheet according to ASTM E 1643, and the <br />manufacturer's written instructions. Seams shall be lapped and sealed in <br />accordance with ASTM E 1643. <br />4. The CONTRACTOR shall exercise care to avoid puncturing or tearing the <br />vapor barrier during installation. Patch punctures and tears as they occur. <br />C. Joints in Concrete: <br />1. All joints shall be installed where indicated on the Drawings or where otherwise <br />approved by the Engineer. The surface of the construction joint shall be rough <br />and prior to placement shall be cleaned and moistened with water. <br />2. Concrete surfaces upon or against which concrete is to be placed, where the <br />placement of the concrete has been stopped or interrupted so that, as <br />determined by the ENGINEER, the new concrete cannot be incorporated <br />integrally with that previously placed, are defined as construction joints. The <br />surfaces of horizontal joints shall be given a compacted, roughened surface for <br />good bonding. Except where the Drawings call for joint surfaces to be coated, <br />the joint surfaces shall be cleaned of all laitance, loose or defective concrete, <br />foreign material, and be roughened to a minimum 1/4-inch amplitude. Such <br />cleaning and roughening shall be accomplished by hydroblasting or <br />sandblasting (exposing aggregate) followed by thorough washing. Pools of <br />water shall be removed from the surface of construction joints before the new <br />concrete is placed. <br />3. After the surfaces have been prepared, all approximately horizontal <br />construction joints shall be covered with a 6-inch lift of a pea gravel mix. The <br />mix shall be placed and spread uniformly. Wall concrete shall follow <br />immediately and shall be placed upon the fresh pea gravel mix. If high range