<br />All oil and gasoline pipelines, power, and telephone or the communication cable
<br />ducts, gas and water mains, irrigation lines, sewer lines, storm drain lines, poles,
<br />and overhead power and communication wires and cables encountered along the
<br />line of the work shall remain continuously in service during all the operations under
<br />the Contract, unless other arrangements satisfactory to the Engineer are made
<br />with the owner of said pipelines, duct, main, irrigation line, sewer, storm drain, pole,
<br />or wire or cable. The Contractor shall be responsible for and shall repair all
<br />damage due to its operations, and the provisions of this Section shall not be
<br />abated even in the event such damage occurs after backfilling or is not discovered
<br />until after completion of the backfilling.
<br />1.04 SITE CLEANLINESS
<br />A. Dust Abatement - The Contractor shall furnish all labor, equipment, and means
<br />required and shall carry out effective measures wherever and as often as
<br />necessary to prevent its operation from producing dust in amounts damaging to
<br />property, cultivated vegetation, or domestic animals, or causing a nuisance to
<br />persons living in or occupying buildings in the vicinity. The Contractor shall be
<br />1 05/08 01505 -2 05 -4893
<br />due to such operations. The Contractor shall take all possible precautions for the
<br />protection of unforeseen utility lines to provide for uninterrupted service and to
<br />provide such special protection as may be necessary.
<br />F. In case it shall be necessary to move the property of any public utility or franchise
<br />'
<br />holder, such utility company or franchise holder will, upon request of the
<br />Contractor, be notified by the Owner to move such property within a specified
<br />reasonable time. When utility lines that are to be removed are encountered within
<br />the area of operations, the Contractor shall notify the Engineer a sufficient time in
<br />advance for the necessary measures to be taken to prevent interruption of service.
<br />'
<br />G. Where the proper completion of the work requires the temporary or permanent
<br />removal and /or relocation of an existing utility or other improvement that is
<br />indicated, the Contractor shall remove and, without unnecessary delay, temporarily
<br />'
<br />replace or relocate such utility or improvement in a manner satisfactory to the
<br />Engineer and the owner of the facility. In all cases of such temporary removal or
<br />relocation, restoration to former location shall be accomplished by the Contractor in
<br />'
<br />a manner that will restore or replace the utility or improvement as nearly as
<br />possible to its former locations and to as good or better condition than found prior
<br />'
<br />to removal.
<br />H. Existing utility lines that are indicated or the locations of which are made known to
<br />the Contractor prior to excavation and that are to be retained, and all utility lines
<br />'
<br />that are constructed during excavation operations shall be protected from damage
<br />during excavation and backfilling and, if damaged, shall be immediately repaired or
<br />replaced by the Contractor at the Contractor's expense. Sewer laterals are
<br />'
<br />included.
<br />I. All repairs to a damaged utility or improvement are subject to inspection and
<br />'
<br />approval by an authorized representative of the utility or improvement owner before
<br />being concealed by backfill or other work.
<br />I
<br />All oil and gasoline pipelines, power, and telephone or the communication cable
<br />ducts, gas and water mains, irrigation lines, sewer lines, storm drain lines, poles,
<br />and overhead power and communication wires and cables encountered along the
<br />line of the work shall remain continuously in service during all the operations under
<br />the Contract, unless other arrangements satisfactory to the Engineer are made
<br />with the owner of said pipelines, duct, main, irrigation line, sewer, storm drain, pole,
<br />or wire or cable. The Contractor shall be responsible for and shall repair all
<br />damage due to its operations, and the provisions of this Section shall not be
<br />abated even in the event such damage occurs after backfilling or is not discovered
<br />until after completion of the backfilling.
<br />1.04 SITE CLEANLINESS
<br />A. Dust Abatement - The Contractor shall furnish all labor, equipment, and means
<br />required and shall carry out effective measures wherever and as often as
<br />necessary to prevent its operation from producing dust in amounts damaging to
<br />property, cultivated vegetation, or domestic animals, or causing a nuisance to
<br />persons living in or occupying buildings in the vicinity. The Contractor shall be
<br />1 05/08 01505 -2 05 -4893