<br />WHEREAS, the City is now paying for materials used in the construction of the
<br />project, totaling Eight Hundred Fourteen Thousand Six Hundred Forty-Seven Dollars
<br />($814,647.00), directly to the Subcontractor; and
<br />
<br />WHEREAS, Change Order No. 3 to the Agreement with Coastal Construction
<br />Company for the construction of the Heritage Park and Parking Garage Project, decreased the
<br />amount of the Agreement by Eight Hundred Fourteen Thousand Six Hundred Forty-Seven
<br />Dollars ($814,647.00), attached hereto as Exhibit "A", bringing the total contract amount not
<br />to exceed to Six Million Six Hundred Seven Thousand Four Hundred Fourteen Dollars and
<br />Eighty-Eight Cents ($6,607,414.88) for the parking garage, unless amended by prior approval
<br />of the City; and
<br />
<br />WHEREAS, Change Order No. 4 to the Agreement with Coastal Construction
<br />Company for the construction of the Heritage Park and Parking Garage Project, was to begin
<br />construction on the Park portion of the Park and for additional work to be performed including
<br />demolition of the Public Works building and Park site, additional sitework, concrete work, and
<br />electrical work which increased the amount of the Agreement by One Million Four Hundred
<br />Fifty-Four Thousand Four Hundred Seventy-Nine Dollars ($1,454,479.00), attached hereto as
<br />Exhibit "A", bringing the total contract amount not to exceed to Eight Million Sixty-One
<br />Thousand Eight Hundred Ninety-Three Dollars and Eighty-Eight Cents ($8,061,893.88) for
<br />the parking garage and park, unless amended by prior approval of the City; and
<br />
<br />WHEREAS, Change Order No. 5 to the Agreement with Coastal Construction
<br />Company for the construction of the Heritage Park and Parking Garage Project, increased the
<br />amount of the Agreement by Two Million Six Hundred Five Thousand Five Hundred Ninety-
<br />Five Dollars ($2,605,595.00), bringing the total contract amount not to exceed to Ten Million
<br />Six Hundred Sixty-Seven Thousand Four Hundred Eighty-Eight Dollars and Eighty-Eight
<br />Cents ($10,667,488.88) for the parking garage and park, unless amended by prior approval of
<br />the City; and
<br />
<br />WHEREAS, the City is now paying for materials used in the construction of the
<br />project, totaling Five Hundred Eighty-Nine Thousand Four Hundred Four Dollars and Nine
<br />Cents ($589,404.09) directly to the Subcontractors; and
<br />
<br />WHEREAS, Change Order No. 6 to the Agreement with Coastal Construction
<br />Company for the construction of the Heritage Park and Parking Garage Project, decreases the
<br />amount of the Agreement by Five Hundred Eighty-Nine Thousand Four Hundred Four Dollars
<br />and Nine Cents ($589,404.09), attached hereto as Exhibit "A", bringing the total contract
<br />amount not to exceed to Ten Million Seventy-Eight Thousand Eighty-Four Dollars and
<br />Seventy-Nine Cents ($10,078,084.79) for the parking garage, unless amended by prior
<br />approval of the City; and
<br />
<br />WHEREAS, the overall contract amount approved under Resolution No. 2009-1434
<br />for the construction of the park and parking garage for Heritage Park remains the same, in an
<br />amount not to exceed Nine Million Two Hundred Fifty Thousand Dollars ($9,250,000.00).