(including those who are to furnish principal items of materials or equipment) proposed for those portions of the
<br />Work as to which the identity of Subcontractors and other persons and organizations must be submitted as specified
<br />in the Contract Documents. Within thirty (30) working days after receiving the list, the CITY will notify the
<br />CONTRACTOR in writing if the CITY, after due investigation, has reasonable objection to any Subcontractor,
<br />person, or organization on such list. The failure of the CITY to make objection to any Subcontractor, person, or
<br />organization on the list within thirty (30) days of the receipt shall constitute an acceptance of such Subcontractor,
<br />person or organization. Acceptance of any such Subcontractor, person or organization shall not constitute a waiver
<br />of any right of the CITY to reject defective Work, material or equipment, or Work, material or equipment not in
<br />conformance with the requirements of the Contract Documents.
<br />2.11 If, prior to the Notice of Award, the CITY has reasonable objection to and refuses to accept any
<br />Subcontractor, person or organization listed, the apparent low BIDDER may, prior to Notice of Award either (i)
<br />submit an acceptable substitute without an increase in their bid price.
<br />ARTICLE 3 - CORRELATION INTERPRETATION AND INTENT OF CONTRACT_ DOCUMENTS
<br />3.1 It is the intent of the Specifications and Drawings to describe a complete Project to be constructed in
<br />accordance with the Contract Documents. The Contract Documents comprise the entire Agreement between the
<br />CITY and the CONTRACTOR They may be altered only by a Modification.
<br />3.2 The Contract Documents are complementary; what is called for by one is as binding as if called for by all. If
<br />CONTRACTOR finds a conflict, error or discrepancy in the Contract Documents, they shall call it to the CITY'S
<br />attention in writing at once and before proceeding with the Work affected thereby; however, they shall not be liable
<br />to CITY for their failure to discover any conflict, error or discrepancy in the Specifications or Drawings. The
<br />various Contract Documents shall be given precedence in case of conflict, error or discrepancy, as follows: Change
<br />Orders, Supplemental General Conditions, Agreement Modifications, Addenda, Special Conditions, Instructions to
<br />BIDDERS, General Conditions, Specifications and Drawings. If the requirements of other Contract Documents
<br />are more stringent than those of the Supplemental General Conditions, the more stringent requirements shall apply.
<br />3.3 The words "fumish" and "furnish and install ", "install ", and "provide" or words with similar meaning shall be
<br />interpreted, unless otherwise specifically stated, to mean "furnish and install complete in place and ready for service ".
<br />3.4 Miscellaneous items and accessories which are not specifically mentioned, but which are essential to produce
<br />a complete and properly operating installation, or usable structure or plant, providing the indicated function, shall
<br />be furnished and installed without change in the Contract. Price. Such miscellaneous items and accessories shall be
<br />of the same quality standards, including material, style, finish, strength, class, weight and other applicable
<br />characteristics, as specified for the major component of which the miscellaneous item or accessory is an essential
<br />part, and shall be approved by the CITY before installation. The above requirement is not intended to included
<br />major components not covered by or inferable from the Drawings and Specifications
<br />3.5 The Work of all trades under this Contract shall be coordinated by the CONTRACTOR in such manner as to
<br />obtain the best workmanship possible for the entire Project, and all components of the Work shall be installed or
<br />erected in accordance with the best practices of the particular trade.
<br />3.6 The CONTRACTOR shall be responsible for making the construction of habitable structures under this
<br />Contract rain proof; and for making equipment and utility installations properly perform the specified function.
<br />If they are prevented from so doing by any limitations of the Drawings or Specifications, the CONTRACTOR shall
<br />immediately notify the CITY in writing of such limitations before proceeding with construction in the area where
<br />the problem limitation exists.
<br />00710-5
<br />
|