RESOLUTION NO. 2013 -atelged
<br /> A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
<br /> SUNNY ISLES BEACH, FLORIDA,APPROVING CHANGE ORDER
<br /> NO. 14 TO AGREEMENT WITH SHORELINE FOUNDATION,INC.
<br /> FOR THE NEWPORT FISHING PIER DEMOLITION AND
<br /> CONSTRUCTION PROJECT, IN AN AMOUNT NOT TO EXCEED
<br /> THIRTY-EIGHT THOUSAND ONE HUNDRED TWO DOLLARS
<br /> AND EIGHT CENTS (538,102.08); AUTHORIZING THE CITY
<br /> MANAGER TO DO ALL THINGS NECESSARY TO EFFECTUATE
<br /> THIS RESOLUTION; PROVIDING FOR AN EFFECTIVE DATE.
<br /> WHEREAS, on September 16, 2010 via Resolution No. 2010-1605, the City Commission
<br /> approved an Agreement with Shoreline Foundation, Inc. to provide professional construction
<br /> services for the demolition and construction of the Historic Sunny Isles Beach/Newport Fishing Pier
<br /> at Pier Park, in an amount not to exceed Three Million Seven Hundred Seventy-Seven Thousand
<br /> Eight Hundred Sixty-Six Dollars ($3,777,866.00); and
<br /> WHEREAS,on June 21,2012 via Resolution No.2012-1927 the City Commission approved
<br /> Change Order Numbers 1-4 with Shoreline Foundation, Inc., decreasing the Agreement amount by
<br /> Eight Hundred Eighteen Thousand One Hundred Fifty-Eight Dollars and Seventy-Nine Cents
<br /> ($818,158.79). bringing the total Agreement amount not to exceed to Two Million Nine Hundred
<br /> Fifty-Nine Thousand Seven Hundred Seven Dollars and Twenty-One Cents ($2,959,707.21); and
<br /> WHEREAS,on June 21,2012 via Resolution No. 2012-1928 the City Commission approved
<br /> Change Order No. 5 with Shoreline Foundation, Inc., increasing the Agreement in an amount not to
<br /> exceed Thirty-Seven Thousand Six Hundred Five Dollars ($37,605.00), bringing the total amount
<br /> not to exceed to Two Million Nine Hundred Ninety-Seven Thousand Three Hundred Twelve Dollars
<br /> and Twenty-One Cents ($2,997,312.21); and
<br /> WHEREAS,on July 19,2012 via Resolution No.2012-1942 the City Commission approved
<br /> Change Order No. 6 to install eight (8) 18" round auger cast piles increasing the Agreement in an
<br /> amount not to exceed Thirteen Thousand Two Hundred Ninety-Eight Dollars and Forty-Six Cents
<br /> ($13,298.46), and increasing the contract time by fifteen(15)days, bringing the total amount not to
<br /> exceed to Three Million Ten Thousand Six Hundred Ten Dollars and Sixty-Seven Cents
<br /> ($3,010,610.67); and
<br /> WHEREAS, on November 15, 2012 via Resolution No. 2012-2000 the City Commission
<br /> approved Change Order No. 7 for painting of the pier and for additional costs for the Permitted Set
<br /> of Design Drawings issued on July 19, 2012 in an amount not to exceed Seven Hundred Sixty-Four
<br /> Thousand One Hundred Dollars and Forty Cents($764,100.40),and increasing the contract time by
<br /> one hundred twenty-seven (127) calendar days; and
<br /> WHEREAS, the City wishes to paint the piles of the pier to add color uniformity to the
<br /> Newport Pier, in an amount not to exceed Thirty-Eight Thousand One Hundred Two Dollars and
<br /> Eight Cents ($38,102.08), and approve Change Order No. 14 with Shoreline Foundation, Inc.,
<br /> bringing the total contract amount not to exceed to Three Million Eight Hundred Twelve Thousand
<br /> Eight Hundred Thirteen Dollars and Fifteen Cents ($3,812,813.15).
<br /> R2013-Shoreline CO 8 Pier Page 1 of 2
<br />
|