CHANGE ORDER <br />No. 11 <br />PROJECT: Newport Fishing Pier Demolition & Construction <br />DATE OF ISSUANCE: 11/21/12 EFFECTIVE DATE: 10/05/12 <br />OWNER: City of Sunny Isles Beach <br />OWNER CONTRACT NO.: 10 -07 -02 <br />CONTRACTOR: Shoreline Foundation, Inc <br />ENGINEER CONTRACT NO.: 11 -4239 <br />ENGINEER: Calvin, Giordano & Associates, <br />Inc. <br />You are directed to make the following changes in the Contract Documents <br />Description: Direct Purchase Option for Saftron DPO 1 3- 00001 7 1 -001 <br />Reason for Change Order: Direct Purchase Option <br />Attachments: DPO 13- 0000171 -001 <br />CHANGE IN CONTRACT PRICE: <br />CHANGE IN CONTRACT TIMES: <br />Original Contract Price <br />Original Contract Times <br />$3,777,866.00 <br />Substantial Completion: 330 calendar days <br />Ready for final payment: 360 calendar days <br />days or dates <br />Net changes from previous Change Orders No. -0- No. -10- <br />Net change from previous Change Orders No. -0- No. -10- <br />$ (315 954.03) <br />142 <br />day. <br />Contract Price prior to this Change Order <br />Contract Times prior to this Change Order <br />Substantial Completion: 472 calendar days <br />$3,461,911.97 <br />Ready for final payment: 502 calendar days <br />days or dates <br />Net increase of this Change Order <br />Net Increase of this Change Order <br />$(26,340.011 <br />0 <br />days <br />Contract Price with all approved Change Orders <br />Contract Times with all approved Change Orders <br />Substantial Completion: 472 calendar days <br />$3,435,571.96 <br />Ready for final payment: 502 calendar days <br />days or dates <br />ECOMMENDED: <br />By: <br />Joel Wadsworth <br />Calvin, Gior ano & ss ciates, Inc. <br />Date: ti/ 1 l-? <br />PPROVE <br />8y: <br />Chris Russo <br />City of Sunny Isles Beach <br />ACCEPTED: <br />By: <br />q ame Royo <br />Shore ne Fou Inc. <br />Date <br />