Subtask E.5 — Incorporate FP &L Design (60 %): Upon delivery from FP &L, CONSULTANT shall <br />incorporate FP &L's proposed improvements into the Underground Plan. Prior to delivery from <br />FP &L, CONSULTANT shall identify FP &L's requirements to anticipate proposed features to <br />coordinate with features of other utilities. <br />Subtask E.6 — Coordinate with Utilities, FP &L and FDOT (90 %): Upon incorporating, proposed <br />design features of proposed improvements will be distributed for final coordination and approval <br />from each of the utilities and FDOT. In addition, FDOT's lighting plan, which is to be provided by <br />others with sufficient detail, will be coordinated with proposed utility improvements. Minor <br />corrections and details are expected to make the Underground Plan complete. <br />Subtask E.7 — Schedule & Project Management Plan: Because of the complexity of this project <br />with its multiple variables and tasks, complicated by long lead times and constraints on delivery, a <br />schedule of sufficient detail is necessary to ensure success. CONSULTANT shall identify <br />components of the project and show dependency upon one another in addition to identifying <br />critical milestones and work plan to meet schedule demands. CONSULTANT shall utilize and <br />maintain schedule on a monthly basis and monitor progress and provide regular updates to City's <br />Project Manager. <br />TASK 3 — Prepare Construction Documents: <br />Subtask E.8 — Prepare Plans for Construction (100 %): Upon approval and input from <br />stakeholders, utilities and CLIENT, CONSULTANT shall prepare final construction plans based <br />upon an approved Underground Plan. Plans shall incorporate sufficient detail for construction of <br />proposed improvements and be used as basis for bids and permits. Because FDOT's RRR project <br />will include resurfacing immediately following installation of underground utilities, plans shall call for <br />proper backfill and compacted, but with only a restored asphalt section. <br />Subtask E.9 — Provide Updated Cost Estimate: Using construction plans, CONSULTANT shall <br />prepare an itemized cost estimate of proposed improvements. This cost estimate is to be used as <br />the engineer's estimated cost for bidding purposes. <br />Note: The above services do not include undergrounding of overhead Transmission Lines. BY their nature, <br />undergrounding of Transmission Lines involve more significant issues and are handled within a separate division within <br />FP &L. To avoid impacting progression of undergrounding efforts, Transmission Lines will not be addressed wdhin the <br />above scope of services. <br />5 �►►1 a KEITH and SCHNARS, P.A. <br />ENGINEERS, PLANNERS, SURVEYORS <br />Professional Services Agreement <br />Project Name: Utility Undergrounding Consulting -Phase II <br />Proiect Location: Sunny Isles Beach, ' L <br />K&S Proposal No.: P509B.MK <br />Revised June 4, 2013 Page 5 <br />