My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
4 - 2.3 Schedule
SIBFL
>
City Clerk
>
Bids-RFQ-RFP
>
ITB
>
(19-01-01) Gateway Park Center
>
Responses
>
TGSV Enterprises
>
Tab 4 Approach
>
Approach
>
4 - 2.3 Schedule
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
3/13/2019 3:34:55 PM
Creation date
3/13/2019 3:34:48 PM
Metadata
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
5
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Activity ID Activity Name Performance % <br />Complete <br />Original <br />Duration <br />Early Start Early Finish Late Start Late Finish Total Float <br />RYDER TRAUMA CENTER FORTIFICATION - Update 3RYDER TRAUMA CENTER FORTIFICATION - Update 37.29%561d 21-Nov-14 11-Feb-16 30-Sep-14 11-Feb-16 0d <br />01400.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d <br />01401.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d <br />01402.00 ADVERSE WEATHER DAYS 100%2d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d <br />01403.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d <br />01404.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d <br />01405.00 ADVERSE WEATHER DAYS 100%2d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d <br />01406.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d <br />01407.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d <br />01408.00 ADVERSE WEATHER DAY 100%1d 21-Nov-14 20-Nov-14 21-Nov-14 20-Nov-14 0d <br />09200.00 FRAMING MATERIALS DELIVERED 100%1d 21-Nov-14 20-Nov-14 09-Oct-14 08-Oct-14 -31d <br />09202.00 FRAMING DELAY 100%23d 21-Nov-14 11-Feb-16 09-Oct-14 11-Feb-16 0d <br />06210.00 REPLACEMENT OF DAMAGED SHEATHING 100%5d 04-Dec-14 03-Dec-14 09-Oct-14 08-Oct-14 -38d <br />07200.00 INSTALLATION OF VISQUEEN 100%5d 04-Dec-14 03-Dec-14 09-Oct-14 08-Oct-14 -38d <br />09900.00 PREP/PAINT STEEL ANGLES 100%5d 04-Dec-14 03-Dec-14 09-Oct-14 08-Oct-14 -38d <br />09201.00 READY TO COMMENCE FRAMING 100%0d <br />COMMENCEMENTCOMMENCEMENT 33.47%557d 21-Nov-14 11-Feb-16 30-Sep-14 11-Feb-16 0d <br />01000.00 OBTAIN EXECUTED CONTRACT 100%5d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d <br />01005.00 BUY-OUTS & SUBCONTRACTS 100%39d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d <br />01010.00 OBTAIN PERMIT 100%44d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d <br />01015.00 RE-LOCATE HELI-PAD TO GROUND (BY <br />OTHERS) <br />100%44d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d <br />01030.00 CHANGE ORDERS 15.95%370d 21-Nov-14 11-Feb-16 30-Sep-14 11-Feb-16 0d <br />01050.00 MOBILIZATION 100%5d 21-Nov-14 20-Nov-14 30-Sep-14 29-Sep-14 -38d <br />01020.00 NOTICE TO PROCEED 100%0d <br />SUBMITTALS & PROCUREMENTSUBMITTALS & PROCUREMENT 10.24%294d 21-Nov-14 17-Apr-15 30-Sep-14 11-Sep-15 105d <br />PREPARE/SUBMITPREPARE/SUBMIT 75.79%214d 21-Nov-14 22-Dec-14 30-Sep-14 17-Aug-15 168d <br />01800-A PREPARE/SUBMIT - SITE PLAN 100%10d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d <br />02810-A PREPARE/SUBMIT - LAWN IRRIGATION 70%10d 21-Nov-14 25-Nov-14 05-Aug-15 07-Aug-15 175d <br />02820-A PREPARE/SUBMIT - FENCING 0%10d 21-Nov-14 08-Dec-14 04-Aug-15 17-Aug-15 174d <br />02900-A PREPARE/SUBMIT - LANDSCAPING 0%10d 21-Nov-14 08-Dec-14 16-Jul-15 29-Jul-15 161d <br />03300-A PREPARE/SUBMIT - CONCRETE 100%10d 21-Nov-14 20-Nov-14 21-May-15 20-May-15 123d <br />03310-A PREPARE/SUBMIT - REBAR 100%20d 21-Nov-14 20-Nov-14 21-May-15 20-May-15 123d <br />04200-A PREPARE/SUBMIT - MASONRY 100%10d 21-Nov-14 20-Nov-14 02-Oct-14 01-Oct-14 -36d <br />05200-A PREPARE/SUBMIT - STRUCTURAL STEEL 80%20d 21-Nov-14 26-Nov-14 08-Apr-15 13-Apr-15 92d <br />Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F Mar Apr May Jun Jul Aug S Oct N Dec Jan F MarApr <br />2014 2015 2016 <br />12-Feb-16, RYDER TRAUMA CENTER FORTIFICATION - Update 3 <br />ADVERSE WEATHER DAY <br />ADVERSE WEATHER DAY <br />ADVERSE WEATHER DAYS <br />ADVERSE WEATHER DAY <br />ADVERSE WEATHER DAY <br />ADVERSE WEATHER DAYS <br />ADVERSE WEATHER DAY <br />ADVERSE WEATHER DAY <br />ADVERSE WEATHER DAY <br />FRAMING MATERIALS DELIVERED <br />FRAMING DELAY <br />REPLACEMENT OF DAMAGED SHEATHING <br />INSTALLATION OF VISQUEEN <br />PREP/PAINT STEEL ANGLES <br />READY TO COMMENCE FRAMING, 15-Oct-14 A, <br />04-Feb-16, COMMENCEMENT <br />OBTAIN EXECUTED CONTRACT <br />BUY-OUTS & SUBCONTRACTS <br />OBTAIN PERMIT <br />RE-LOCATE HELI-PAD TO GROUND (BY OTHERS) <br />CHANGE ORDERS <br />MOBILIZATION <br />NOTICE TO PROCEED, 01-Sep-14 A, <br />15-Apr-15, SUBMITTALS & PROCUREMENT <br />22-Dec-14, PREPARE/SUBMIT <br />PREPARE/SUBMIT - SITE PLAN <br />PREPARE/SUBMIT - LAWN IRRIGATION <br />PREPARE/SUBMIT - FENCING <br />PREPARE/SUBMIT - LANDSCAPING <br />PREPARE/SUBMIT - CONCRETE <br />PREPARE/SUBMIT - REBAR <br />PREPARE/SUBMIT - MASONRY <br />PREPARE/SUBMIT - STRUCTURAL STEEL <br />Actual Level of Effort <br />Actual Work <br />Remaining Work <br />Critical Remaining Work <br />START DATE 06-Dec-13, FINISH DATE 12-Feb-16 <br />DATA DATE 21-Nov-14, RUN DATE 25-Aug-17 <br />PAGE 1 OF 26
The URL can be used to link to this page
Your browser does not support the video tag.