My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
ITB 21-08-01 Utility Undergrounding Golden Shores (final)
SIBFL
>
City Clerk
>
Bids-RFQ-RFP
>
ITB
>
(21-08-01) Utility Undergrounding Conversion for Golden Shores
>
ITB 21-08-01 Utility Undergrounding Golden Shores (final)
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
9/1/2021 10:14:46 AM
Creation date
9/1/2021 10:11:02 AM
Metadata
Fields
Template:
CityClerk-Bids_RFP_RFQ
Project Name
Utility Undergrounding Conversion for Golden Shores
Bid No. (xx-xx-xx)
21-08-01
Project Type (Bid, RFP, RFQ)
Bid
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
287
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
<br />01310 - 1/6 <br />SECTION 01310 - CONSTRUCTION SCHEDULES <br />PART 1 - GENERAL <br />1.01 SCOPE: <br />A. Construction Progress Schedule: The Contractor shall submit a detailed work <br />progress schedule showing all work in a graphic format suitable for displaying <br />scheduled and actual progress. The Engineer will review and comment on the <br />schedule. Upon agreement, the Contractor shall furnish the Engineer prints of the <br />accepted schedule. The Contractor shall not change the accepted work progress <br />schedule without prior concurrence of the Engineer. The schedule shall show actual <br />progress and any proposed changes in the schedule of the remaining work. <br />B. The WORK under this contract will be planned, scheduled, executed, and reported <br />by the CONTRACTOR using a cost-loaded CPM (Critical Path Method) schedule <br />with a coding structure specified by the CITY. The CONTRACTOR will adhere to <br />established technical standards for CPM scheduling using a computerized <br />precedence diagram method. The CONTRACTOR is required to provide baseline <br />and status data using in hard copy and electronic (CD disk) format as specified <br />herein. <br />C. The CONTRACTOR is responsible for coordinating its own schedules (including <br />subcontractors) as well as the construction activities of others as required to fully <br />execute the Work. The CITY’S goal is to maintain the overall Construction Program <br />Schedule, of which the CONTRACTOR’S Construction Schedule will be a part. <br />1.02 SOFTWARE/INTERFACE REQUIREMENTS: <br />A. The CONTRACTOR shall use CPM scheduling software to produce the contract <br />schedules and reports as specified herein. This software shall be Primavera <br />Enterprise Scheduling Software (P3e/c) or a compatible format such as Primavera <br />Contractor, or approved equal. <br />B. Within ten calendar (10) days of the Notice of Award, the CONTRACTOR shall <br />submit, for review and approval by the CITY, descriptive information on the proposed <br />CPM software to be used. <br />1.03 QUALITY ASSURANCE: <br />A. The CONTRACTOR shall perform the work covered by this Section with personnel <br />having substantial experience in the use of computer based scheduling programs on <br />construction projects for the development and maintenance of the schedule <br />throughout the project duration. <br />B. It is the responsibility of the CONTRACTOR to work with each subcontractor and <br />supplier to obtain information pertinent to the planning and updating of their <br />respective activities in the schedules. <br />1.04 DEALING WITH SUBSTITUTES: <br />A. All versions of the CONTRACTOR’S schedule (including Construction Schedule <br />Revisions) shall be based solely on the WORK as awarded, and shall exclude any <br />substitute proposals, even if the CONTRACTOR pursues a substitution in <br />accordance with the provisions of the Contract.