7.6. The Contractor shall obtain and pay for all permits, fees and licenses <br />necessary and ordinary for the Work save and except as set forth herein. <br />The Contractor shall comply with all lawful requirements applicable to the Work and shall <br />give and maintain any and all notices required by applicable law pertaining to the Work. <br />7.7 Supervision <br />7.7.1. The Contractor shall employ and maintain at the Project site only competent <br />supervisory personnel. Absent written instruction from the Contractor to the contrary, the <br />superintendent shall be deemed the Contractor's authorized representative at the site and <br />shall be authorized to receive and accept any and all communications from the City or the <br />Engineer / Architect. <br />7.7.2. Key administrative, managerial and supervisory personnel assigned by the <br />Contractor to this Project are as follows: <br />Name Fu nction <br />/ nn49 <br />oA+�lq�tc� �G ��t c�k12r��4 <br />The Contractor shall furnish to the City complete resumes of each of the individuals named <br />above. So long as the individuals named above remain actively employed or retained by the <br />Contractor, they shall perform the functions indicated next to their names unless the City <br />agrees to the contrary in writing or unless the City requests the removal of any such <br />individual from the Project. In the event the City requests the removal of any of the <br />individuals named above, the Contractor shall immediately comply and shall immediately <br />replace such individual with a qualified substitute to whom the City makes no objection. In <br />the event one or more individuals not listed above subsequently assumes one or more of <br />those functions listed above, the Contractor shall be bound by the provisions of this <br />Subparagraph 7.7.2 as though such individuals had been listed above. <br />7.8. The Contractor, within fifteen (15) days of commencing the Work, shall submit <br />to the City and the Engineer / Architect for their information, the Contractor's schedule for <br />completing the Work. The Contractor's schedule shall be presented in the critical path <br />(CPM) format. The Contractor's schedule shall be revised no less frequently than monthly <br />(unless the parties otherwise agree in writing) and shall be revised to reflect conditions <br />encountered from time to time and shall be related to the entire Project. Each such revision <br />Page 17 of 43 <br />