<br />after the occurrence of the event or the first appearance of the condition giving rise to the
<br />claim and shall set forth in detail the Contractor's basis for requiring additional time in
<br />which to complete the Project. Said claim shall specifically include, among other things,
<br />an adjusted critical path (CPM) schedule reflecting precisely the delay and its claimed
<br />impact upon the Contractor's future performance. In the event the delay to the Contractor
<br />is a continuing one, only one notice and claim for additional time shall be necessary. If the
<br />Contractor fails to make such claim as required in this Subparagraph, any claim for an
<br />extension of time shall be waived.
<br />8.3.5.1 In no event, and under no circumstances, shall the Contract Price be
<br />increased for, nor shall the Contractor claim, recover, or receive payment for, any
<br />cost, expense, damages, or compensation of any kind by reason of any delay to the
<br />Project, whether critical or non -critical, and whether caused in whole or in part by
<br />the City other than as set forth in Paragraph 8.3.5 above. The Contractor shall not
<br />be entitled to any direct, indirect, consequential, impact, or other costs, expenses,
<br />or damages, including but not limited to, costs of acceleration or inefficiency,
<br />arising because of delay, disruption, interference, or hindrance from any cause
<br />whatsoever, whether such delay, disruption, interference, or hindrance be
<br />reasonable or unreasonable, foreseeable, or unforeseeable, or avoidable or
<br />unavoidable.
<br />It is further agreed that such direct costs do include the Contractor's home office
<br />overhead, loss of efficiency, consequential damages, or equipment costs in excess
<br />of actual equipment rental paid by the Contractor to a third party. The Contractor's
<br />sole and exclusive remedy for delay, hindrance, and disruption shall be an extension
<br />of the Contract Time provided a claim for same is made and is allowable pursuant
<br />to the provisions of Paragraph 8.3.5 hereinabove.
<br />8.4 Field Orders
<br />8.4.1 The City's Representative after first obtaining approval from the City, shall
<br />have authority to order minor changes in the Work not involving, a change in the Contract
<br />Price or in - Contract Time and not inconsistent with the intent of the Contract. Such
<br />changes shall be affected by Field Order and shall be binding upon the Contractor. The
<br />Contractor shall carry out such Field Orders promptly.
<br />ARTICLE IX
<br />SUBCONTRACTORS
<br />9.1 Definition
<br />9.1.1 A Subcontractor is an entity that has a direct contract with the Contractor
<br />to perform a portion of the Work.
<br />9.2 Award of Subcontracts
<br />9.2.1 Upon execution of the Contract, or as may be required by the Instructions
<br />to Bidders, the Contractor shall furnish the City, in writing, the names of persons or