Laserfiche WebLink
<br />01020 - 5/11 <br /> <br /> <br />Measurement for payment shall be based on the linear feet of conduit installed measured <br />as LF along the horizontal center line of the conduit installed. Payment shall be based at <br />the total unit price bid per linear foot of conduit installed. <br /> <br />Items 15: <br />Install Feeder Splice Box (material furnished by FPL) / EA: FPL will provide necessary <br />splice boxes for this task. CONTRACTOR responsible for coordination and acceptance of <br />deliveries. The price for these items shall include but not limited to all labor, equipment <br />and materials necessary to handle, store, install and construct the structure in accordance <br />with these contract documents which include but not limited to locating, verifying and <br />protecting existing utilities, excavation, removal and disposal of unsuitable material below <br />the structure. Completed installation includes sod replacement, soft digs, test pits, and <br />exploratory digging for existing utilities, repairs to irrigation systems, landscape, driveway, <br />curb and sidewalk, striping and pavement markings, appurtenances and incidentals as <br />shown on the plans and specifications and/or necessary for a complete installation shall <br />be included in the unit price for this pay item. <br /> <br />Measurement for payment shall be based upon the actual number of boxes installed in <br />accordance with the contract documents. Payment shall be at the unit price bid per each. <br /> <br />Items 16: <br />Install Vista Switch Cabinet (material furnished by FPL) / EA: FPL will provide <br />necessary Vista Cabinets for this task. CONTRACTOR responsible for coordination and <br />acceptance of deliveries. The price for these items shall include but not limited to all labor, <br />equipment and materials necessary to handle, store, install and construct the structure in <br />accordance with these contract documents which include but not limited to locating, <br />verifying and protecting existing utilities, excavation, removal and disposal of unsuitable <br />material below the structure. Completed installation includes sod replacement, soft digs, <br />test pits, and exploratory digging for existing utilities, repairs to irrigation systems, <br />landscape, driveway, curb and sidewalk, striping and pavement markings, appurtenances <br />and incidentals as shown on the plans and specifications and/or necessary for a complete <br />installation shall be included in the unit price for this pay item. <br /> <br />Measurement for payment shall be based upon the actual number of Vistas installed in <br />accordance with the contract documents. Payment shall be at the unit price bid per each. <br /> <br />Items 17 : <br />Install 50” Splice Box (material furnished by FPL) / EA: FPL will provide necessary <br />splice boxes for this task. CONTRACTOR responsible for coordination and acceptance of <br />deliveries. The price for these items shall include but not limited to all labor, equipment <br />and materials necessary to handle, store, install and construct the structure in accordance <br />with these contract documents which include but not limited to locating, verifying and <br />protecting existing utilities, excavation, removal and disposal of unsuitable material below <br />the structure. Completed installation includes sod replacement, soft digs, test pits, and <br />exploratory digging for existing utilities, repairs to irrigation systems, landscape, driveway,