Laserfiche WebLink
verified and approved by the Owner prior to installation, the IC shall <br />provide and install valve box extension(s) as manufactured by Ametek. <br />3.07 THRUST BLOCK INSTALLATION <br />A. All mainline pipe shall have thrust blocks installed at tees, bends, or at the <br />end of pipe lines as detailed on the drawings. Care shall be taken to <br />install the concrete on the fittings and away from joints of pipe. Control, <br />power, and valve wires must be kept free of concrete and placed outside <br />and away from the thrust blocks. Thrust blocks shall be poured against <br />undisturbed ground as detailed on the drawings. No pre -cast or pre - <br />"bagged" thrust blocks will be allowed. <br />MYTIMIM <br />A. Exterior alkyd - enamel, flat - black, shall be used on above - ground PVC <br />risers and other designated irrigation equipment. The IC shall provide <br />paint sample prior to execution of painting. <br />3.09 TESTING <br />A. The IC shall notify the LA and Owner seventy -two (72) hours in advance <br />of testing. <br />B. Prior to backfilling of mainline fittings, the IC shall fill the mainline piping <br />with water, in the presence of the Owner /OAR, taking care to purge the air <br />from it by operating all the sprinkler - control valves one (1) or more times <br />and /or such other means as may be necessary. A small, high - pressure <br />pump or other means of maintaining a continuous water supply shall be <br />connected to the mainline and set so as to maintain 125 psi in the <br />mainline system for two (2) hours without interruption. When this has <br />been accomplished, and while the pressure in the system is still 125 psi, <br />leakage testing shall be performed in accordance with AWWA Standard <br />C -600 (i.e., .08 of a gallon (x) diameter of pipe (x) per 1,000' of pipe ( =) <br />allowable amount of water added). Pressure readings shall be noted and <br />make -up water usage shall be recorded. Should the rate of make -up <br />water usage indicate significant leakage, the source of such leakage shall <br />be found and corrected and the system then re- tested until the <br />Owner /OAR is satisfied that the system is reasonably sound. Lateral line <br />testing shall be conducted during the operating testing of the system by <br />checking visually the ground surface until no leaks in this portion of the <br />system are evident. Leaks shall be repaired or paid for by the IC at <br />anytime they appear during the warranty period. <br />C. Adjustment and Coverage of System: Coordinate pressure testing with <br />adjustments and coverage test of system so both may occur at the same <br />07/06 02810 -20 05 -5564 <br />